This document provides an informal guide to the everyday mechanisms underpinning LSST Data Management’s approach to project management. It is intended to be read in conjunction with LDM-465, which provides a formal description of the project management process and requirements.
Important Documents¶
Wherever a conflict arises, baselined project documentation takes precedence over this note. You are encouraged to submit bug reports so that this document can be made compliant.
Be aware of prefixes: “LDM-” documents refer specifically to the Data Management subsystem, “LSE-” to Systems Engineering, “LPM-” to Project Management.
- LPM-43, LPM-44
- WBS Structure and WBS Dictionary, respectively. The former shows the overall work breakdown structure for the whole project.
- LPM-98
- LSST Project Controls System Description. Describes and defines the components of the PMCS used to manage and report on the overall LSST Project.
- LDM-465
- LSST DM Project Management and Tools. The formal, high-level document which defines the project management process used by LSST DM. The present document may be thought of as a guide to applying the principles defined in LDM-465 in practice.
Useful Contacts¶
The LSST DM Project Manager is Jacek Becla. He is the first point of contact for all issues regarding project management within DM.
The LSST Project Controls Specialist is Kevin Long. He is responsible for the PMCS and, in particular, for ensuring that DM properly complies with our earned value management requirements. He is the first point of contact for all questions about the PMCS system.
Technical Managers¶
This guide is primarily aimed at the LSST DM technical managers. Technical managers report directly to the DM Project Manager. Per LDM-465, they are expected to:
- Assemble the team capable of delivering work scoped through the WBS on-time and within budget. Provide daily technical management and leadership for the team, monitor and optimize team performance.
- Work closely with the DM Project Manager on defining short and long-term plan and schedule for their teams. Direct the execution of their team’s plan, ensuring the team delivers on-time and within budget.
- Report group’s activities as required, including reporting to the EVMS used by LSST, and providing input for monthly status reports.
In short, technical managers are, in general, expected to act as CAM and technical lead for their groups; as such, they are sometimes referred to as “T/CAMs”. The role of CAM is defined in detail below.
Formal Organizational Structure¶
Work Breakdown Structure¶
The LSST WBS is defined in LPM-43 (see also LPM-44 for an extended—but not universally illuminating—definition of what each level of the breakdown consists of).
The WBS provides a hierarchical index of all hardware, software, services, and other deliverables which are required to complete the LSST Project. It consists of alphanumeric strings separated by periods. The first component is always “1”, referring the LSST Construction Project. “02C” in the second component corresponds to Data Management Construction. Subdivisions thereof are indicated by further digits. Subdivisions at this level correspond to teams within the DM project. Thus:
WBS | Description | Lead Institution |
---|---|---|
1.02C.01 | System Management | LSST |
1.02C.02 | Systems Engineering | LSST |
1.02C.03 | Alert Production | University of Washington |
1.02C.04 | Data Release Production | Princeton University |
1.02C.05 | Science User Interface | Caltech IPAC |
1.02C.06 | Science Data Archive | SLAC |
1.02C.07 | Processing Control & Site Infrastructure | NCSA |
1.02C.08 | International Communications. & Base Site | NCSA & LSST |
1.02C.09 | Systems Integration & Test | LSST |
These subdivisions are referred to as the third level WBS. Often, they are quoted without the leading “1” (e.g. “02C.01”), but, even in this form, they are referred to as “third level”.
All of these third level WBS elements are subdivided, forming a fourth level. The fourth level always contains a “00” element, which is used to capture management and Level of Effort Work, and may contain other fourth level, or even deeper, structure. Nodes in the WBS tree are referred to as elements.
Organization Breakdown Structure¶
In parallel with the WBS, we have an OBS, which assigns each institution involved in the project a unique numeric identifier. Those directly relevant to DM are:
OBS | Institution |
---|---|
1.01 | LSST |
1.02 | SLAC |
1.03 | Caltech IPAC |
1.04 | NCSA |
1.05 | University of Washington |
1.06 | Princeton University |
The Control Account Manager¶
A control account is the intersection between the WBS and the OBS. Each control account falls under the purview of a CAM. Typically within DM, a single CAM is responsible for the whole of a third level WBS. That is, the manager at the lead institution for a particular component is responsible for all work performed on that WBS element, even if that work is performed at another institution.
Earned Value Principles¶
LSST DM is funded by as an NSF MREFC project. Under the terms of the MREFC award, we are required to follow an earned value approach to project management. A full description of the earned value approach is outside the scope of this document (the project will provide formal training). We provide a brief aide-mémoire for convenience only.
The earned value technique assigns each component of the system with a dollar value corresponding to its expected cost of production. In a (largely) software based project like LSST DM, it is often convenient to equate the cost of production with the cost of the labor required to write the code: in the more general case, however, it also includes cost of hardware procurements, etc. This provides a convenient heuristic for estimating cost: given some nominal labor costs, the cost of a component is a proxy for the amount of labor required to produce it.
As well as a cost, the plan includes a start date and a completion date for each component.
The total value of work which should have been completed by a particular date is the BCWS. The total value of work which has actually been completed by the date is the BCWP. The total sum expended on the work is the ACWP. If estimates of both cost and time for every component of the system are accurate, at the end of construction, all of these three quantities will be equal.
In practice, estimation is rarely perfect. Imperfect estimates are exposed as variances. Specifically, we can show either SV (defined as BCWP-BCWS; a negative value means that less of the system has been delivered to date than planned) or CV (defined as BCWP-ACWP; a negative value means that the work delivered to date has been more expensive than predicted). Related quantities, SPI and CPI, express the same information as ratios rather than sums. In general, we strive to achieve variances of near zero: even a positive variance (corresponding being ahead of schedule or being cheaper than expected) is indicative of an inaccurate plan.
All of these indices can be applied to any WBS element within the project. Thus, we can talk about value earned across the whole of DM (1.02C) or on a specific component (say, the User Workspace Toolkit, 1.02C.05.05).
Labor Costs¶
Our methodology is designed to avoid exposing individual salaries to the wider project. Therefore, when calculating labor costs for earned value purposes, we do not rely on a known cost per individual. Instead, all staff are assigned to one of a small number of types (scientist, senior scientist, developer, senior developer), each of which is assigned a nominal cost level which does not vary between individuals, or, indeed, across institutions. This nominal cost does not correspond to a particular individual, but is a broadly defined expectation.
Variance Narratives¶
Caution
Confirm exact thresholds with Kevin.
There’s some talk of a 10% threshold, but I believe (per input from Jacek) that it’s not currently enforced. Waiting for Kevin to respond to enquiry.
Every month, the eCAM tool is updated from PMCS to reflect the latest earned value status. If either schedule or cost variance (SV or CV) is more than -$100k, you will be required to provide a “narrative”. This is divided into two parts: you must explain why the variance arose, and what action will be taken to correct it (e.g. slipping work into the future, or diverting resources from elsewhere to make up the shortfall). The narrative is entered directly into eCAM.
Variance is calculated on a monthly basis; variance narratives are due in the second week of the calendar month following that to which they apply (refer to the Standard Reporting Cycle for details).
Level of Effort Work¶
The implicit assumption in the earned value technique outlined above is that all work corresponds to a specific deliverable. However, parts of our work do not: every member of the team will find it necessary to attend meetings or take part in other activities which do not directly map to deployed code. This may be particularly the case for technical managers or others in leadership roles within the project. This work is referred to as LOE: it is assumed to earn value simply through the passage of time.
LDM-465 provides a detailed definition of the types of work it is permissible to regard as LOE. In general, we strive to minimize the fraction of our effort which is devoted to LOE activities and favour those which are more directly accountable.
The assumption encoded in LDM-465 is that developers will spent 30% of their time on LOE type activities, and the remaining 70% of their effort is tracked against concrete deliverables.
All LOE work should be invoiced to the “00” fourth-level WBS element (1.02C.03.00, 1.02C.04.00, etc), which is reserved for “management engineering and integration”. Per the effort estimation procedure, this means that at least 30% of every individual’s time will be invoiced to the 00 element.
Estimating Effort¶
The Project assumes that a full-time individual works for a total of 1,800 hours per year: this figure is after all vacations, sick leave, etc are taken into account. Staff appointed to “developer” positions are expected to devote this effort directly to LSST.
Appointment as a “scientist” includes a 20% personal research time allowance. That is, scientists are expected to devote 1,440 hours per year to LSST, and the remainder of their time to personal research.
Our base assumption is that 30% of an individual’s LSST time (i.e. 540 hours/year for a developer, 432 hours/year for a scientist) are devoted to overhead for meetings, ad-hoc discussions and other interruptions. This work is counted as LOE (and, as such, is charged to the relevant “00” fourth level WBS element, as described here).
Some individuals—notably technical managers themselves, as well as others in leadership roles—are expected to have a larger fraction of their time devoted to LOE work.
Assuming no variation throughout the year, we therefore expect 105 hours of productive work from a developer, or 84 hours from a scientist, per month.
Rather than working in hours, our JIRA based system uses “story points” (SPs), with one SP being defined as equivalent to four hours of effort by a competent developer. Thus, we expect developers and scientists to produce 26.25 and 21 SPs per month respectively. This is summarized in Table 1.
Hours | SPs Per Month | ||
---|---|---|---|
Per Year | Per Month | ||
Developer | 1800 | 105 | 26.25 |
Scientist | 1440 | 84 | 21 |
On occasion, it may be appropriate to tailor the number of SPs expected per unit time from a particular individual. For example:
- Individuals in leadership roles may assign a larger fraction of their time to LOE type work, and therefore spend fewer hours generating SPs. The ratio of hours to story points remains constant, but the number of hours decreases.
- New or inexperienced developers, even when devoting their full attention to story-pointed work, will likely be less productive than their more experienced peers. In this case, the ratio of hours to SPs increases, but the number of hours remains constant.
In either case, the total number of SPs which will will be generated by the team in a given time interval is reduced. This should be taken into account when resource loading.
Long Term Planning¶
Caution
I’m providing just a brief description and references to LDM-465 here because the DMBP project isn’t yet in place. I don’t think it’s appropriate for this document to be normative (i.e. it should describe, rather than define, procedure), and there aren’t yet a list of questions or gotchas to address.
Refer to LDM-465 for a description of the long-term planning system. In brief, the plan for the duration of construction is embodied in:
- A series of planning packages, which describe major pieces of technical work. Planning packages are associated with concrete, albeit high-level, deliverables (in the shape of milestones, below), and have specific resource loads (staff assignments), start dates, and durations. The entire DM system is covered by around 100 of these planning packages.
- Milestones represent the delivery or availability of specific functionality. Each planning package culminates in a milestone, and may contain other milestones describing intermediate results.
Warning
LDM-465 claims that planning packages are defined at the third level WBS. I think this is a mistake.
Planning packages are defined at the fourth level of the WBS breakdown (e.g. at 1.02C.04.02, see the material on the Work Breakdown Structure). They may not cut across the WBS structure, but rather must refer to that particular fourth-level element and its children.
Caution
Who is responsible for deciding the level of a milestone? Can technical managers directly create level 1 milestones? Are technical managers limited to only directly inputting level 4 (or 3, or, …?) milestones, with higher level deliverables defined by the Project Manager/Subsystem Lead?
What is the consequence for missing a milestone? It has no direct earned value impact.
Milestones are defined at a number of levels: see LDM-465 for details. Some of these are exposed to external reviewers: it is vital that these be delivered on time and to specification. Low-level milestones are defined for use within DM, but even here properly adhering to the plan is vital: your colleagues in other teams will use these milestones to align their schedules with yours, so they rely on you to be accurate.
Earned Value and Planning Packages¶
Caution
This is my attempt to think through the issues and figure out the mechanism. It needs Jacek and/or Kevin to confirm if this is what we’re actually doing.
A planning package has a duration and a staff assignment (it is “resource loaded”). Given a (nominal) cost per unit time of the staff involved (see Labor Costs), this translates directly to a BCWS.
During Short Term Planning, effort is drawn from the budget embodied in the planning packages to generate the cycle plan, described in terms of epics: see Defining Epics for details. Each epic itself has a particular budget. This budget is subtracted from that available in the planning package at the point when the epic is defined.
At any given time, the BCWP of a planning package consists of the sum of the BCWP of all epics derived from that package which have been marked complete, together with the fractions of value earned from all epics currently in progress.
An example may serve to illustrate.
Planning package P
is baselined to start at the beginning of F17 and run
through to the end of F18, i.e. a total of three cycles, or 18 months. It has
two members of staff—A
and A
— assigned to it full time. Both share the same
nominal cost of $X
per cycle.
The BCWS for the total planning package is the cost per cycle multiplied by
the number of cycles: 3 * $2X = $6X
.
In F17, both members of staff are assigned to an epic derived from P
. The
BCWS of the epic is $2X
. The remaining value in the planning package is
$4X
.
At the end of F17, the epic is completed. The BCWP and ACWP are both $2X
.
The work is on cost and on schedule: there is no variance.
In S18, A
is reassigned and is unable to work on a new epic derived from
P
. B
continues the work alone, completing an epic worth $X
by the
end of the cycle. The BCWP and ACWP are now both $3X
; there is no cost
variance. However, the BCWS is $4X
: compared to the original schedule for
the planning package, there is a schedule variance of -$X
. There is a
total of $3K
left in the planning package.
In F18, C
joins the project. C
only costs $0.5X
per cycle, but is
a fast worker: she can complete in one cycle work that would take A
or
B
two cycles.
B
and C
work together through F18. The ACWP for the cycle is
$1.5X
; the BCWP is $3X
. The ACWP to date $4.5X
. The BCWP and BCWS
are both $6X
. At this point, the project is complete: there is no schedule
variance, and a cost variance of +$1.5X
.
Short Term Planning¶
Per LDM-465, short term planning is carried out in blocks referred to as cycles, which (usually) last for six months. Before the start of a cycle, technical managers work with the DM Project Manager and the Project Controls Specialist to ensure their plan for the cycle is well defined in both JIRA and PMCS.
Defining The Plan¶
Scoping Work¶
The first essential step of developing the short term plan is to produce an outline of the programme of work to be executed. In general, this should flow directly from the long term plan, ensuring that the expected planning packages are being worked on and milestones being hit.
While developing the cycle, please:
- Do not add artificial padding or buffers to make the schedule look good;
- Do budget appropriate time for handling bugs and emergent issues;
- Reserve time for planning the following cycle: it will have to be defined before this cycle is complete;
- Leave time for other necessary activities, such as cross-team collaboration meetings and writing documentation.
Obviously, ensure that the programme of work being developed is achievable by your team in the time available: ultimately, you will want to compare the number of SPs your team is able to deliver with the sum of the SPs in the epics you have scheduled, while also considering the skills and availability of your team. It is better to under-commit and over-deliver than vice-versa, but, ideally, aim to estimate accurately.
Defining Epics¶
As described in LDM-465, the plan for a six month cycle fundamentally consists of a set of resource loaded epics defined in JIRA. Each epic loaded into the plan must have:
- A concrete, well defined deliverable or be clearly described as a “bucket”;
- The
cycle
field set to the appropriate cycle; - The
WBS
field set to the appropriate WBS leaf element. - The
Story Points
field set to a (non-zero!) estimate of the effort required to complete the epic in terms of SPs (see above).
Be aware that:
- An epic may only be assigned to a single cycle. It is not possible to define an epic that crosses the cycle boundary (see Closing the Cycle for the procedure when an epic is not complete by the end of the cycle).
- An epic may only be assigned to a single WBS leaf element. It is not possible to define epics that cover multiple WBS elements. See Cross Team Work for information on scheduling work which requires resources from multiple elements.
- An epic must descend from a single planning package (see Long Term Planning).
- Although LOE work should be charged to the 00 fourth-level element, this does not imply that other work cannot be charged here. Indeed, where possible management activities should be scheduled as epics with concrete deliverables in this element rather than being handled as LOE.
- The epic should be at an appropriate level of granularity. While short epics (a few SPs) may be suitable for some activities, in general epics will describe a few months of developer-time. Epics allocated multiple hundreds of story points are likely too broad to be accurately estimated.
The Project Controls Specialist will automatically pull information from JIRA to populate PMCS with the plan.
Note
Epics which do not satisfy the above criteria may be defined in JIRA. These will not be pulled into PMCS, will not form part of the scheduled plan, and will not earn value. However, they may still be useful for organizing other work, sketching plans for future cycles, etc: please feel define them as necessary.
In order to fully describe the plan to PMCS, epics require information that is not captured in JIRA. Specifically, it is necessary to define:
- Start and end dates for the epic;
- Staff assignments.
Note
Although it is possible—indeed, encouraged—to set the assignee
field in
JIRA to the individual who is expected to carry out the bulk of the work in
an epic, this does not provide sufficient granularity for those cases when
more than one person will be contributing.
This information is most conveniently captured in per-team spreadsheets which are supplied to the Project Controls Specialist before the start of the cycle. Spreadsheets describing previous cycles are stored in Google Drive: a convenient way to get started would be to use one of those as a template.
The spreadsheets used capture epic start and end dates at monthly granularity. This can lead to a variance when monthly results are tabulated (it builds in the assumption that epics start at the beginning of a month, so even an intentional start mid-month will look like a deviation from the schedule). In practice, this variance is likely to be small, and should average out by the end of the cycle, when all epics should be closed on schedule. However, if this becomes a problem, it is possible to fine-tune dates by directly consulting with the Project Controls Specialist.
Note
When loading epics at the start of a cycle, it is not necessary that they be fully loaded with stories: these can be defined during the cycle. You do, of course, need to have thought through the contents of the epic in enough detail to provide an overall SP estimate, though.
Bucket epics¶
Some work is “emergent”: we can predict in advance that it will be necessary, but we cannot predict exactly what form it will take. The typical example of this is fixing bugs: we can reasonably assume that bugs will be discovered in the codebase and will need to be addressed, but we cannot predict in advance what those bugs will be.
This can be included in the schedule by defining a “bucket” epic in which stories can be created when necessary during the course of a cycle. Make clear in the description of the epic that this is its intended purpose: every epic should either have a concrete deliverable or be a bucket.
Bucket epics have some similarities with LOE work. As such, we acknowledge that they are necessary, but seek to minimize the fraction of our resources assigned to them. If more than a relatively small fraction of the work for a cycle is assigned to bucket epics, please consider whether this is really necessary and appropriate.
Mapping SPs to BCWS¶
Caution
I think this is correct, but please check.
As discussed above, the amount of work to be performed is estimated in terms of SPs, while the earned value system accounts for work in terms of budgeted cost (BCWS). In order to estimate the value earned by completing an epic, it is necessary to map from one to the other.
The outline of the calculation here is straightforward: SPs map to developer hours. Given the staff assignment for the epic, the number of hours scheduled per developer can be calculated. Given the nominal costs associated with each developer, the total labor cost can be estimated.
Therefore, we calculate the number of hours of each staffing grade being assigned to the epic, multiply that by the cost per hour of that grade, and that provides the cost of the work scheduled.
Cross Team Work¶
Planning epics are always assigned to a particular WBS leaf element: they do not span elements or teams. It is therefore impossible to schedule a single epic which covers cross-team work. There are two ways to approach this problem:
- The technical managers for both teams to be involved in the work schedule epics separately, within their own WBS structure. They are responsible for agreeing start and end dates, deliverables and resourcing between themselves. From the point of view of the PMCS, these epics are independent pieces of work which happen to be coincident.
- With agreement between technical managers, an individual may be detached from one team and explicitly work for another team for some defined period. One technical manager is therefore responsible for defining and scheduling their work. Their “home” manager will charge actuals against the WBS supplied by the manager manager of the receiving team.
Regardless of the approach taken, technical managers should be especially careful to ensure that cross-team work is well defined. Usually, it is convenient for a single manager to take ultimate responsibility for ensuring that it is successfully delivered.
Revising the Plan¶
During the cycle, it is possible that changing circumstances will cause reality not to exactly match with the plan. This will ultimately cause a variance, which should be avoid and which—if it becomes significant enough—will require a narrative.
After the plan for the cycle has been entered into JIRA, it is under change control: it can only be altered through a LCR approved by the CCB. In order to reschedule (or remove entirely from the cycle) an epic which has not yet started, the technical manager should work with the Project Controls Specialist to prepare and submit an appropriate LCR to the monthly CCB meeting.
Note that it is not possible to alter history by means of an LCR. That is, if the scheduled start date of an epic is already in the past, it is not possible to move it into the future using a change request. In this case, there is no option but to carry the variance related to the late start of the epic into the future, to describe that with narratives where necessary, and to attempt to address the variance as soon as is possible.
Based on the above, it is clear that technical managers should closely track performance relative to the plan throughout the cycle, and proactively file change requests to avoid running variances wherever possible.
Closing the Cycle¶
Assuming everything has gone to plan, by the end of a cycle all epics should be marked as “done”. When an epic is marked as done, it is equivalent to having delivered the required functionality. The total cost of that functionality—the BCWS, calculated as per Mapping SPs to BCWS—is now claimed as value earned.
Epics which are in progress at the end of the cycle cannot be closed until they have been completed. These epics will spill over into the subsequent cycle. It is not appropriate to close an in-progress epic with a concrete deliverable until that deliverable has been achieved: instead, a variance will be shown until the epic can be closed. Obviously, this will impact the labor available for other activities in the next cycle. (This does not apply to bucket epics, which are, by their nature, timeboxed within the cycle).
Similar logic applies to epics which have not been started: if the planned start date is in the past, they can no longer be rescheduled by means of an LCR. They must be completed at the earliest possible opportunity; you will show a variance until this has been done.
Execution¶
Caution
The description below focuses on a sprint-based monthly cadence. I think, based on LDM-465, that this is globally applicable. However, I’m not sure if some teams (NCSA, SQuaRE?) don’t sprint, and I’m not sure what subtleties are introduced by Kanban rather than Scrum. Please check!
Caution
The LDM-465 draft mentions various concepts that aren’t currently standard practice (reports during all hands standups, a central DM board, scripts for monitoring the status of JIRA, etc). This document aims to be descriptive rather than normative, so these are not discussed here. After a fleshed-out policy has been developed, we can add them.
Having thus defined the plan for a cycle, we execute it by means of a series of month-long sprints. In this section, we detail the procedures teams are expected to follow during the cycle.
Defining Stories¶
Epics have already been defined as part of the cycle plan. However, the epic is not at an appropriate level for scheduling day-to-day work. Rather, each epic is broken down into a series of self-contained “stories”. A story describes a planned activity worth between a small fraction of a SP and several SPs (more than about 10 is likely an indication that the story has not been sufficiently refined). It must be possible to schedule a story within a single sprint, so no story should ever be allocated more than 26 SPs.
The process for breaking epics down into stories is not mandated. In some circumstances, it may be appropriate for the technical manager to provide a breakdown; in others, they may request input from the developer who is actually going to be doing the work, or even hold a brainstorming session involving the wider team. This is a management decision.
It is not required to break all epics down into stories before the cycle begins: it may be more appropriate to first schedule a few exploratory stories and use them to inform the development of the rest of the epic. However, it is required that all stories which will be worked in an upcoming sprint are defined before the sprint starts.
Note that there is no relationship enforced between the SP total estimated for the epic and the sum of the SPs of its constituent stories. It is therefore possible to over- or under-load an epic. This will have obvious ramifications for the schedule. See Earning Value for its impact on earned value.
Sprinting¶
Caution
Do we actually require that a sprint be one month long? Why?
Each team organizes its work around month-long periods called sprints. A sprint comprises a defined collection of stories which will be addressed over the course of the month. These stories are not necessarily (indeed, not generally) all drawn from the same epic: rather, while epics divide the cycle along logical grounds, sprints divide it along the time axes.
Broadly, executing a sprint falls into three stages:
Preparation.
The team assigns the work that will be addressed during the sprint by choosing from the pre-defined stories. Each team member should be assigned a plausible amount of work, based on the per-story SP estimates and the likely working rate of the developer (see Estimating Effort).
The process by which work is assigned to team members is a local management decision: the orthodox approach is to call a team-wide meeting and discuss it, but other approaches are possible (one-to-one interactions between developers and technical manager, managerial fiat, etc).
Do not overload developers. The sprint should describe a plausible amount of work for the time available.
Execution.
Daily management during the sprint is a local decision. Suggested best practice includes holding regular “standup” meetings, at which developers discuss their current activities and try to resolve “blockers” which are preventing them from making progress.
Stories should be executed following the instructions in the Developer Guide as regards workflow, coding standards, review requirements, and so on. It is important to ensure that completed stories are marked as “done”: experience suggests that this can easily be forgotten as developers rush on to the next challenge, but it is required to enable us to properly track earned value.
Avoid adding more stories to a sprint in progress unless it is unavoidable (for example, the story describes a critical bug that must be addressed before proceeding).
Review.
At the end of the sprint, step back and consider what has been achieved. What worked well? What did not? How can these problems be avoided for next time? Was your estimate of the amount of work that could be finished in the sprint accurate? If not, how can it be improved in future? Refer to the burn-down chart for the sprint, and, if it diverged from the ideal, understand why.
Again, the form the review takes is a local management decision: it may involve all team members, or just a few.
We use JIRA‘s Agile capabilities to manage our sprints. Each technical manager is responsible for defining and maintaining their own agile board. The board may be configured for either Scrum or Kanban style work as appropriate: the former is suitable for planned development activities (e.g. Science Pipelines development); the latter for servicing user requests (e.g. providing developer support).
Handling Bugs & Emergent Work¶
Receiving Bug Reports¶
Members of the project who have access to JIRA may report bugs or make feature requests directly using JIRA. As discussed under JIRA Maintenance, technical managers should regularly monitor JIRA for relevant tickets and ensure they are handled appropriately.
Our code repositories are exposed to the world in general through GitHub. Each repository on GitHub has a bug tracker associated with it. Members of the public may report issues or make requests on the GitHub trackers. Per the Developer Workflow, all new work must be associated with a JIRA ticket number before it can be committed to the repository. It is therefore the responsibility of technical managers to file a JIRA ticket corresponding to the GitHub ticket, to keep them synchronized with relevant information, and to ensure that the GitHub ticket is closed when the issue is resolved in JIRA.
The GitHub issue trackers are, in some sense, not a core part of our workflow, but they are fundamental to community expectations of how they can interact with the project. Ensure that issues reported on GitHub are serviced promptly.
In some cases, the technical manager responsible for a given repository is obvious, and they can be expected to take the lead on handling tickets. Often, this is not the case: repositories regularly span team boundaries. Work together to ensure that all tickets are handled.
Issue Types¶
We have previously referred to day-to-day work being described by means of stories. However, JIRA provides us with two additional issue types: “bug” and “improvement”. Per RFC-43 and , the semantics of the various issue types are:
- A story is the result of breaking down an epic into workable units;
- A bug describes a fault or error in code which has already been accepted to master;
- An improvement describes a feature request or enhancement which has not been derived by breaking down the long term plan (i.e., it is an ad-hoc developer or user request).
The three issue types are functionally equivalent: these semantic distinctions are for convenience only, and are not rigorously enforced.
In particular, note that all issue types are equivalent in terms of the data which is loaded to PMCS: it makes no distinction between them. Marking a bug or improvement as done has exactly the same impact on the global earned value state as would completing an equivalent story.
Scheduling¶
In some cases, a ticket may describe emergent work which must be immediately by adding it to a bucket epic. In other cases, it can be deferred to a later cycle, or, after appropriate discussion, may be regarded as inappropriate (and can be tagged as Invalid or Won’t Fix). This is a management decision. When closing a ticket as inappropriate, please take a moment to describe why—the individual who reported it will appreciate an explanation of why it has been rejected, and it will serve as a useful reference the next time somebody suggests the same thing.
A special case of inappropriate tickets are those that duplicate work which has already been described elsewhere. Please close these as Invalid, and add a JIRA link of type “duplicates” to the original ticket.
Relationship to Earned Value¶
We adopt the position that bugs are a natural part of the software lifecycle, and hence addressing them at an appropriate level earns value in the same way as new software development. That is, SPs earned by working on bugs and completing bucket epics contribute to earned value in the same way as other work.
However, bugs do serve as an bellwether for software quality issues. It would obviously be inappropriate—and a severe source of schedule risk—for the value earned from addressing bugs in existing software to dominate the productivity of the team at the expense of new development. We expect that no more than around 30% of schedulable developer time will be dedicated addressing bugs: any more than this must be carefully justified.
Earning Value¶
The basic procedure for earning value during the cycle is akin to that discussed earlier for long term planning.
In short, as we have seen, the BCWS for a particular epic is defined by its estimated (i.e. attached to the epic before work commences) SP total and its staff assignment. When an epic is marked as complete, this is the value that is earned.
The BCWP for an epic is calculated based on the fractional
completeness of an epic. That is, if an epic has a total SP count of X
,
and the total of stories marked as complete within it is Y
, then BCWP =
BCWS * Y / X
.
Be aware that stories that marked as “invalid” or “won’t fix” in JIRA are not included in this calculation: they earn no value.
As we have seen, it is not required that the total SPs of all the stories contained within an epic (the “planned SPs”) is equal to the total SP estimate of the epic itself (“estimated SPs”). Further, it is permitted to add stories to (or, indeed, remove stories from) the epic during the cycle. In these cases, we hold to two basic tenets:
- No epic can ever be more than 100% complete;
- Completeness cannot decrease. That is, if an epic has been registered as 90% complete, adding more stories cannot make it less complete than before.
In order to meet these criteria, the relative weights of stories will be automatically adjusted on ingest to the PMCS. The detailed algorithm by which this adjustment is made is not publicly documented.
JIRA Maintenance¶
At any time, new tickets may be added to JIRA by team members. Please remind
your team of the best practice in this respect (RFC-147 and ). It is the
responsibility of technical managers to ensure that new tickets are handled
appropriately, updating the schedule to include them where necessary. It is
required that the Team
field be set to the appropriate team
(RFC-145 and ). Please regularly monitor JIRA for incomplete tickets and
update them appropriately. Where tickets describe bugs or other urgent
emergent work which cannot be deferred, refer to Handling Bugs & Emergent Work.
Coordination Standup¶
Attention
I’ve not included the meeting URL here, since the tech note will be publicly available.
The technical managers meet with the Project Manager and interested others (it is not a closed meeting) twice every week. This is a forum to discuss general project management issues, but, in particular, to resolve issues which cut across team boundaries and are relevant for the ongoing sprint.
Meetings take place using Google Hangouts at a pre-arranged URL. Meetings take place at 11:00 (11 a.m.) Project (Pacific) Time on Tuesdays and Fridays.
Monthly Progress Narratives¶
Every calendar month, each technical manager is required to support the Project Manager with a report on the activities of their group. This report should be generally submitted no later than the second week of the month (refer to the Standard Reporting Cycle), but this may be moved earlier on occasion. You are encouraged to submit your report as early in the month as possible.
Submit your report by editing the template for the appropriate month on Google Docs. You need to fill in all the sections with your name attached; when complete, remove your name. Provide a per-WBS breakdown of work over the month being reported on and plans for the upcoming month, as well as describing any recruitment activities (positions opened, interviews conducted, appointments made, etc). Refer to previous reports for examples of the style used (but note that they are not not always consistent).
Reporting Actuals¶
In order to comply with the earned value management system, it is necessary to track the actual cost of work being performed (the “actuals”) in each leaf element of the WBS. That is, whenever an invoice is issue from a subcontracting institution to AURA, it must be broken down into dollar charges against individual WBS elements.
Some institutions rigorously track how staff are spending their time (e.g. by filling in timesheets), and may directly make that information available to AURA as part of the invoicing process. In this case, the technical manager need take no further action.
Other institutions do not rigorously check staff activity and/or do not supply this information to AURA when invoicing. In this case, the technical manager is responsible for breaking down the invoice by WBS and forwarding that to the relevant AURA contracts officer (check with the project manager if you are unsure who that is).
A typical invoice breakout should be supplied in a spreadsheet similar to that shown in Table 2.
Invoice Voucher | Salary | Fringe xx% | Materials & Services | F & A yy% | Total | WBS | 02C.0N.00 | 02C.0N.01 | 02C.0N.02 | TOTAL |
---|---|---|---|---|---|---|---|---|---|---|
Invoice Date YYYY-MM-DD | ACCOUNT | KLM20N00A | KLM20N01A | KLM20N02A | ||||||
Invoice Period YYYY-MM-DD – YYYY-MM-DD | $ABCDE.FG | $HIJKL.MN | $OPQRS.TU | $VWXYZ.AB | $CDEFG.HI | AMOUNT | $12345.67 | $89012.34 | $56789.01 | $158147.02 |
Note that when reporting actuals at this level it is not required to provide a mapping from dollar values to individuals who did the work. However, it is important to note that, should the Project be audited in the future, it is perfectly possible that they will wish to examine such a mapping. You should therefore keep records which will enable you to provide it upon request.
Note that when loading the plan at the start of a cycle (as described here), you are expected to provide the names of the individuals who will be carrying out the work. It is not, in general, appropriate to charge for labor from individuals who have not been named in this way, even if the total sum comes in below the budgeted amount specified in your contract. In some special cases (e.g. temporary work carried out by summer students) it may be possible to make an exception: please discuss this with the project manager on a case-by-case basis.
Standard Reporting Cycle¶
During the first week of the calendar month, data from JIRA together with actual costs (labor charges, etc) are ingested to the PMCS system. This indicates the progress of all activities and shows any Earned Value variances. This information is made available to technical managers through eCAM.
During the second week of the calendar month:
- Variance Narratives, where necessary, must be submitted through eCAM.
- Monthly Progress Narratives must be submitted through Google Docs.
The DM Project Manager assembles extended and summary reports, based on the reports received from the institutions. The extended report is periodically examined by Federal auditors, while the summary report is provided to senior management and the AMCL for review.
Staffing Changes¶
In addition to onboarding procedures at your local institution, please be aware of
- The LSST New Employee Onboarding material, and
- The DM Developer Onboarding Checklist
and direct new recruits to them when they join your team.
We maintain a spreadsheet listing all members of the DM team. Ensure it is kept up to date with the current and projected staffing within your team.
Glossary¶
- ACWP
- Actual Cost of Work Performed (often referred to as “actuals”).
- AMCL
- AURA Management Committee for LSST.
- BCWP
- Budgeted Cost of Work Performed.
- BCWS
- Budgeted Cost of Work Scheduled.
- Budgeted (labor) unit
- An hour of work.
- CAM
- Control Account Manager. A CAM is responsible for the scope, schedule and budget for one or more control accounts.
- CCB
- Change Control Board. All changes to the baselined plan must be approved by the CCB. See LPM-19 for details.
- Control Account
- An intersection point between the WBS and the OBS. For example, work performed at IPAC (1.03) on the Science User Interface (1.02C.05) is managed by a single control account.
- CPI
- Cost Performance Index. Defined as BCWP/ACWP.
- CV
- Cost Variance. Defined as BCWP-ACWP.
- Cycle
- The time period over which detailed, short-term plans are defined and executed. Normally, cycles run for six months, and culminate in a new release of the LSST Software Stack, however this need not always be the case.
- eCAM
- The eCAM Notebook, a tool which reports information from the PMCS. It provides a convenient view of the current status of the project in terms of EVMS.
- Element
- A node in the hierarchical project WBS.
- Epic
- A self contained work with a concrete deliverable which my be scheduled to take place with a single cycle and WBS element.
- EVMS
- Earned Value Management System. See the brief description above, or refer to formal training.
- JIRA
- Issue and project tracking software produced by Atlassian. LSST’s JIRA is a core interface between technical managers, their teams, and the PMCS.
- LCR
- LSST Change Request. It is necessary to submit a change request to alter any “baselined” aspect of the project. This includes, for example, altering change controlled plans, or epics that have been loaded to PMCS.
- LOE
- Level of Effort. LOE work is that which does not correspond to a specific deliverable. A detailed definition is provided in LDM-465; see also the discussion above.
- MREFC
- Major Research Equipment and Facilities Construction. The terms under which LSST’s NSF funding has been issued; we are required to strictly adhere to these.
- NSF
- National Science Foundation.
- OBS
- Organizational Breakdown Structure; see the definition above.
- PMCS
- Project Management Control System. The PMCS is not a single piece of software, but rather an interlocking suite of tools. In general, the CAM need not interact with PMCS directly, but only through the eCAM and JIRA tools: it is safe to treat PMCS as a “black box”. Occasionally, individual PMCS components such as Primavera or Deltek Cobra escape this abstraction and appear in documentation.
- Resource Loading
- Assigning particular resources (in software development, almost always staffing) to particular tasks. A “resource loaded plan” provides a mapping of resources to the plan throughout execution.
- SP
- Story Point. Used to estimate the duration of tasks in JIRA. One SP is equivalent to 4 hours of uninterrupted effort by a competent developer.
- SPI
- Schedule Performance Index. Defined as BCWP/BCWS.
- Sprint
- A month-long period of work for a particular team.
- Story
- A JIRA issue type describing a scheduled, self-contained task worked as part of an epic. Typically, stories are appropriate for work worth between a fraction of a SP and 10 SPs; beyond that, the work is insufficiently fine-grained to schedule as a story. While fractional SPs are fine, all stories involve work, so the SP total of an in progress or completed story should not be 0.
- SV
- Schedule Variance. Defined as BCWP-BCWS.
- Timebox
- A limited time period assigned to a piece of work or other activity. Useful in scheduling work which is not otherwise easily limited in scope, for example research projects or servicing user requests.
- WBS
- Work Breakdown Structure; see the discussion above.